專案時間組合合理化的六步驟


關鍵字:關鍵路徑、進度壓縮、依賴關係。


來源:PMI Community Post  Quick Quiz

 

“No matter how careful I am, the estimated timeframes for my projects are always too long. What am I doing wrong?

A. Cut each team member’s estimate by 10%, as they have probably padded the time.

B. Never give an estimate as to how long it will take to complete a project.

C. Always plan at least one hour of overtime per employee per day.

D. Follow a checklist of suggestions to quickly see ways to reduce the schedule time.


Answer: D. Follow a checklist of suggestions to quickly see ways to reduce the schedule time.



解題:


一但PM已經完成專案進度時程表(project schedule),

再利用下列的六個步驟的檢查表以縮短專案專案進度時程表,而不必變更專案範圍。


1.   分配額外的資源(Assign additional resources)

2.   分配重要任務額外的時間(Assign critical task overtime)

3.   改變任務關係(Change task relationships)

4.   改變工作時間(Change working times)

5.   改變重要任務的持續時間(Change the duration of a critical task)



I:

1.   進度管理計劃

2.   活動資源要求

3.   資源日曆

4.   專案進度網路圖

5.   活動清單

6.   活動屬性

7.   活動持續時間估算


T&T:


1  分配額外的資源

    額外的資源可以讓專案更快速的進行。但,這額外的資源可能會增加專案成本。

    若專案時間的長短是組織最關心的事項,則這個增加的成本可能是值得的。

2  分配重要任務額外的時間

    關鍵路徑是專案裡最長的那一條路徑。進度壓縮只有對關鍵路徑上的任務進行,才會有效果。

    注意,地區性或文化性的工作習慣會影響PM的可選擇空間,如回教徒或猶太人在某些時間是不允許工作的。

    以及工會對加班的態度。

3  改變任務關係

    PM可試著改變活動的四種依賴關係。

    快速跟進是可考慮採用的方式之一(但需注意衍生的風險)。

    改變活動的依賴關係後,前置時間(提早一點開始)、延遲時間(晚一點開始)都可以讓任務產生較短的時間組合。

4  改變工作時間

    所有的資源都可考慮增加它們的工作時間,可採用的有延長工時:

    如提早上班、延後下班、縮短午休時間、周末日工作、三班制工作等方式。

5  改變重要任務的持續時間

    一個經驗豐富的團隊成員可以較快速的完成指派的工作,但必需瞭解經驗較豐富的人意味著較高的薪資成本。

    專案開始後PM可要求團隊成員從新估算活動完成所需的時間。因為這時對活動的困難度或其所需的時間會有

    更佳的瞭解。

6  拆解任務

    首先檢視關鍵任務。如果可以將其拆解成更細的活動,你是否可以改變原先的工作順序?

    是否可以把原先一個人做的工作指派給較多的人分攤?

    例如:製作訓練手冊這項任務,可以拆解為訂購紙張、列印內容、印封面、裝訂。

    因此,此項任務可改變原先順序並指派給不同的資源。

O

1.  更新的專案進度表

2.  更新的活動清單

3.  更新的活動屬性

4.  更新的專案日曆

5.  變更請求

6.  更新的進度基準

7.  更新的進度管理計劃


 